Hello Guys,

i am getting this below error while generating amounts from the Action field to create Financial cost budget in the Oracle Project Planning and Control/ Project Management. Can you please help me with this.

"Amounts cannot be generated because no source financial plan is available" .

Thanks,
Kishore
Attachments (1)
Comment
There are no comments made yet.
Accepted Answer Pending Moderation
Hello Kishore
Please check whether the Budget has been baselined first.

Secondly, under which EBS instance version/release you are getting this error?
Regards
Kabeer Khan
Comment
There are no comments made yet.
  1. more than a month ago
  2. Oracle Financials
  3. # 1
Accepted Answer Pending Moderation
Hi Kabeer,

Thanks for the response. Issue has been rectified and Can you please tell me how to submit the Draft Budget for the Project Manager Approval in PJM.


Thanks,
Kishore
Comment
There are no comments made yet.
  1. more than a month ago
  2. Oracle Financials
  3. # 2
Accepted Answer Pending Moderation
Hello Kishore
Good to know that the issue got resolved. For your new query I suggest you to raise a separate thread.
Regards
Kabeer Khan
Comment
There are no comments made yet.
  1. more than a month ago
  2. Oracle Financials
  3. # 3
  • Page :
  • 1


There are no replies made for this post yet.
However, you are not allowed to reply to this post.